The public lands fight
Data centers on public land: what just happened, and where each fight stands.
39 events on the record across 11 fights, 24 of them federal and 8 at the state level, and 16 sites that sit on land the public owns. The newest: Boulder City’s response to BLM’s motion is due, Oct 5, 2026. Headlines land here every fifteen minutes; the timeline is written from primary sources, one entry per step.
This page is a record of the fight over data centers on public land. Public land isn’t a county’s to give or an agency’s to sell, it belongs to everyone, and we’re against data centers on it. These projects move their costs onto people who never got a vote: the ratepayers on the utility, the county downstream of the water, the neighborhood the transmission line crosses. Each fight below says what happened, who decided it, and where it goes next.
The sites on public land
16 sites in the record sit on land the public owns, each placed there by a public document its page links: a BLM decision or right-of-way case, an Energy Department site selection, a state land office action. They carry a pulsing ring on the map. Nothing here is inferred from an overlay.
- Valar Atomics Green River Gigasite (BLM Price Field Office)On public land · Bureau of Land Management, Price Field Office · 10,200 acres · Utahwithdrawn
- Valar Atomics Project Beehive (BLM near Price)On public land · Bureau of Land Management, Utah (Price Field Office area) · 9,000 acres · Utahproposed
- Rhea Data Blacks Creek Campus (BLM Four Rivers)On public land · Bureau of Land Management, Four Rivers Field Office · 3,226 acres · Idahoproposed
- Bergen Data Center (Copia Digital, BLM Las Vegas Field Office)On public land · Bureau of Land Management, Las Vegas Field Office · 744 acres · Nevadaproposed
- Frontier Data Center (Copia Digital, BLM Lower Sonoran Field Office)On public land · Bureau of Land Management, Lower Sonoran Field Office · 620 acres · Arizonaproposed
- Harquahala Data Center (Copia Digital, BLM Lower Sonoran Field Office)On public land · Bureau of Land Management, Lower Sonoran Field Office · 275 acres · Arizonaproposed
- Townsite Solar 2 AI Data Center (Boulder City)On public land · Bureau of Land Management, Las Vegas Field Office · 88.5 acres · Nevadasuspended
- Oakline at Mill Creek (Verrus, Salem)On state land · State of Oregon, Mill Creek Corporate Center · 32 acres · Oregonblocked by moratorium
- DOE Paducah AI Infrastructure SiteOn public land · U.S. Department of Energy, Paducah Site · Kentuckyproposed
- Falcon Data Center (Copia Digital, BLM Shoshone Field Office)On public land · Bureau of Land Management, Shoshone Field Office · Idahoproposed
- Henderson BLM Hyperscale Data Center (Skylar Capital, Paradise Hills)On public land · Bureau of Land Management · Nevadawithdrawn
- On The Mark Data Center (BLM Sierra Front Field Office, Silver Springs)On public land · Bureau of Land Management, Sierra Front Field Office · Nevadaproposed
- PORTS Technology Campus (Piketon)On public land · U.S. Department of Energy, Portsmouth Site · Ohiounder construction
- Savannah River Site ITOn public land · U.S. Department of Energy, Savannah River Site · South Carolinaproposed
- TAP Data Center (Copia Digital, BLM Lower Sonoran Field Office)On public land · Bureau of Land Management, Lower Sonoran Field Office · Arizonaproposed
- Undisclosed BLM Data Center Project (Hermiston)On public land · Bureau of Land Management, Vale District · Oregonproposed
Off public land but tied to it: Project Jupiter (STACK Infrastructure / BorderPlex Digital Assets), crosses state land (New Mexico State Land Office); Monarch Data Center (Copia Power, Mason Valley), crosses public land (Bureau of Land Management, Sierra Front Field Office).
On BLM’s books without a public location yet, as The Washington Sun, September 18, 2026 read the agency’s right-of-way records: Copia Power in Wyoming, a data center proposal, withdrawn by the applicant in summer 2026; Prometheus Hyperscale in Wyoming, rights-of-way for an access road, a telecommunications line and a water pipeline, under BLM review; Valar Atomics in Utah, a second data center with small nuclear reactors, the Raceway gigasite, proposed, size not stated. Each goes on the map the day BLM’s case record or a notice of intent gives it a location.
Coming up
- Nov 3, 2026 Vote
Boulder City votes on data center zoning
Boulder City residents vote on changes to the city’s zoning rules for data centers, the local half of the Townsite fight.
Boulder City, Nevada: the first data center approved on BLM land · Source: Wyoming Public Media
- Dec 31, 2026 Deadline
BLM plans a notice of intent on the Blacks Creek data center by the end of the year
Field manager Jarod Blades said the office plans to publish a notice of intent in the Federal Register before the end of the year, which opens the project to public comment and starts the environmental review.
Blacks Creek, Idaho: 3,200 acres of BLM land south of Boise · Source: Idaho Statesman
- Jul 1, 2027 Deadline
Oregon’s pause on data centers on state land is set to end
The governor’s pause runs through this date unless she issues new direction first.
Oregon’s state land · Source: Oregon Capital Chronicle
Meetings readers have posted
- Dec 3, 2026 Meeting
Save Bren Mar Coalition, Fairfax County Government Center Auditorium, 12000 Government Center Parkway, Fairfax, VA 22035
Wed, Dec 2, 7:30 PM ET. Attend the Planning Commission Public Hearing to Oppose the Edsall Data Center Substation
Where each fight stands
- Oct 5, 2026 Deadline
Boulder City, Nevada: the first data center approved on BLM land
BLM approved an 88.5-acre data center 1.6 miles from Lake Mead on June 26, the first data center BLM has approved on land it manages. The Interior Board of Land Appeals stayed it on September 1, and on September 21 BLM asked the board to set aside its own approval so it can review the application again.
Latest: Boulder City’s response to BLM’s motion is due
Next: Boulder City’s response to BLM’s motion is due October 5; the city votes on data center zoning in November.
- Sep 30, 2026 Announcement
Interior’s list of public land for data centers
Interior told BLM state directors to name parcels that could take data centers and return their lists within three days. The list is still secret, but The Washington Sun read BLM’s right-of-way records and found at least 12 data center proposals on 17,600 acres across six Western states. In September a Texas developer withdrew a 1,000 MW data center and gas plant it had proposed on 680 acres of BLM land at Henderson, Nevada, and NPR reported Valar Atomics’ Project Beehive near Price, Utah: about 456 small reactors and data centers on over 9,000 acres of BLM land, around 9.6 gigawatts, now under BLM review.
Next: The first notice of intent on any of the 12, which is when a location and a size become public.
- Jul 29, 2026 Award
The Energy Department’s federal sites
DOE picked Idaho National Laboratory, Oak Ridge, Paducah and the Savannah River Site for private AI campuses on federal land, and awarded Paducah on July 29.
Latest: DOE awards Paducah to Brookfield and NextEra: 1.8 GW, 2 GW of new gas, over $100 billion
Next: Developer selections at the three other sites.
- Sep 9, 2026 Statement
Mount Hood National Forest and Google’s water
H.R. 655 would hand 150 acres of the Mount Hood National Forest to The Dalles, Oregon, so the city can serve its data centers’ water demand.
Latest: Sen. Wyden comes out against H.R. 655
Next: Senate Energy and Natural Resources holds the bill; Sen. Wyden is against it.
- Aug 27, 2026 Ruling
Cave City, Kentucky, beside Mammoth Cave
A developer sued a town of 2,500 twice over a twelve-month moratorium on a 1.2 GW campus 3.5 miles from Mammoth Cave National Park.
Latest: The Cave City data center suits proceed
Next: The consolidated suits in Barren Circuit Court, annexation first, next on the docket November 23; the moratorium runs to May 2027.
- Sep 8, 2026 Moratorium
Oregon’s state land
Gov. Kotek killed a state land sale to a Google-funded developer in Salem, then paused every data center request on state land through July 2027.
Latest: Oregon pauses every data center request on state land through July 2027
Next: The pause holds through July 1, 2027, or until the governor issues new direction.
- Sep 17, 2026 Statement
New Mexico’s state trust land
The land commissioner refused a data center at Spaceport America while Sierra County’s moratorium stands.
Latest: New Mexico’s Democratic nominee for governor promises a data center pause on her first day
Next: County moratoria across New Mexico; the land commissioner’s office and the governor’s race are both on the November 3 ballot.
- Sep 14, 2026 Deadline
Alaska’s state land at Houston, in the Mat-Su
Alaska proposes handing nearly 20,000 acres near Houston to its own development authority, at no cost and with nobody else allowed to bid, for an industrial district that could take data centers.
Latest: The comment period on the Houston transfer closes with more than 2,100 comments
Next: DNR’s final decision, after a comment period that drew more than 2,100 comments; five senators say the conveyance may not meet the public purpose the statute requires.
- Sep 23, 2026 Statement
Blacks Creek, Idaho: 3,200 acres of BLM land south of Boise
Rhea Data, an Arevia Power subsidiary, applied to build a four million square foot data center campus with its own gas plant on about 3,200 acres of BLM land beside Blacks Creek Reservoir, one of the largest data center proposals on public land yet described in public. Boise’s mayor came out against it on September 23.
Latest: Boise’s mayor comes out against the Blacks Creek data center
Next: BLM’s Four Rivers Field Office plans a notice of intent in the Federal Register before the end of the year, which opens public comment.
- Sep 30, 2026 Vote
Congress
A bill to ban AI data centers on federal land, a bill to end the right-of-way shortcut BLM used at Boulder City, and a run of siting, transparency and cost bills. One cost bill passed the House 417 to 3 on September 16 and was blocked in the Senate the next day. On September 30 Senate Republicans blocked Sen. Wyden’s bill to ban selling or transferring federal land for data centers.
Latest: Senate Republicans block Wyden’s bill to ban selling public land for data centers
Next: The Senate on the Ratepayer Protection Act; committee action on the rest.
- Jul 23, 2025 Order
The White House order
Executive Order 14318 told every federal agency to put federal land to work for data centers. BLM’s Townsite approval cites it.
Latest: The White House orders federal land opened to data centers
Latest headlines
read 8 minutes ago · 40 headlines from 38 outlets in the last ninety days · the outlet’s words, never ours
- In Fairbanks, Interior Secretary Burgum touts deregulation and data centersKTOOOct 15, 9:11 PM ET
- AI data centers are coming for federal land. They’re roiling the Nevada governor’s raceThis Is RenoOct 15, 7:00 PM ET
- Viewpoint: Forstag will protect public land from data centersMissoula CurrentOct 15, 10:17 AM ET
- Interior secretary pitches Fairbanks amid regional power emergencyAlaska’s News SourceOct 15, 1:36 AM ET
- AI Data Center Push on Federal Land Draws Fire in Boulder City and Rural Southern NevadaNevada GlobeOct 14, 6:41 PM ET
- DATA CENTERS: Not on public landCoeur d'Alene PressOct 14, 4:06 AM ET
- AI data centers are coming for federal land and roiling Nevada governor's racePBSOct 13, 2:20 PM ET
- What Alaska can teach us when it comes to dealing with data centersOregon Capital ChronicleOct 13, 2:20 PM ET
- Data centers on public lands are the latest effort in AI raceVernonReporterOct 13, 9:16 AM ET
- AI data centers are coming for federal land. They're roiling the Nevada governor's raceTraverse City Record-EagleOct 13, 8:27 AM ET
- AI data centers are coming for federal land. They are roiling the Nevada governor's raceThe Washington PostOct 13, 7:41 AM ET
- AI data centers are coming for federal land. They are roiling the Nevada governor's race | Business | dailygazette.comThe Daily GazetteOct 13, 7:28 AM ET
- AI Data Centers Threaten Our Federal Public LandsSierra ClubOct 12, 8:20 PM ET
- Why the Wilderness Society Backs a Data Center MoratoriumHeatmap NewsOct 9, 3:17 PM ET
- Rhea data center proposal on public land raises power demand concernswww.arbiteronline.comOct 9, 2:05 PM ET
- Inside Utah’s bid to become the country’s next nuclear hubCenter for Western PrioritiesOct 8, 5:47 PM ET
- Data Centers are Coming for Our Public Lands — How We Fight BackPublic Employees for Environmental Responsibility - PEEROct 7, 2:56 PM ET
- Data centers proposed on federal land in eastern Oregon, Idaho and other Western statesIdaho State JournalOct 7, 1:20 PM ET
- PEER Urges Congress to Use Budget Bill to Block Data Centers on Public LandsPublic Employees for Environmental Responsibility - PEEROct 7, 9:40 AM ET
- Trump-backed startup wants 9,000 acres of public land for data centerPlanetizenOct 7, 9:00 AM ET
- UDWR reports to Public lands council; no filings for Data centers as of nowETV NewsOct 6, 4:48 PM ET
- 9,000-acre nuclear-powered data center proposed on public lands in Utahresilience.orgOct 6, 4:07 AM ET
- Conservation group calls for moratorium on AI data centers on US public lands By ReutersInvesting.comOct 5, 4:56 PM ET
- Conservation group calls for moratorium on AI data centers on US public landsReutersOct 5, 4:41 PM ET
- Celeste Maloy, Kent Udell debate monument downsizing, divvying up Colorado River water, regulating AI in first matchup ahead of midterm electionsThe Salt Lake Tribune · subscriptionOct 3, 8:00 AM ET
- AI Data Center Siting on Federal Lands: An Energy Viewrand.orgOct 2, 11:56 AM ET
- Massive nuclear plant/waste dump/data center complex planned for BLM land in UtahThe Land DeskOct 2, 9:31 AM ET
- Plan for first U.S. data center on public land faces scrutinyThe Center SquareOct 1, 7:45 PM ET
- Startup Seeks More Than 450 Nuclear Reactors on Utah Public Land to Power a Data Center ComplexNature World NewsOct 1, 7:26 PM ET
- Valar Atomics pitches 456-reactor, 9.6-gigawatt data center on federal land in Utahfinance.biggo.comOct 1, 2:30 PM ET
- Nuclear startup plans hundreds of reactors on Utah public landCenter for Western PrioritiesOct 1, 11:32 AM ET
- 9,000-Acre Nuclear-Powered Data Center Proposed on Public Lands in UtahMore Than Just Parks | SubstackOct 1, 10:16 AM ET
- Oregon U.S. Senator Wants to Keep Data Centers off Federal LandFM News 101 KXLOct 1, 8:31 AM ET
- U.S. Senate Republicans Block Senator Ron Wyden’s Bill to Ban Data Centers on Public Lands as Trump Administration Is Considering the Transfer Of More Than 17,000 Acres Of Public Land To Build 12 New Data Centers (Video)Sierra Sun TimesOct 1, 8:03 AM ET
- Planned Data Center on Utah Federal Land Sparks ConcernRTO InsiderSep 30, 8:04 PM ET
- The Rush to Build Data Centers on Public Lands Is Worse Than You ThoughtOutdoor LifeSep 30, 6:41 PM ET
- Senate blocks Wyden's bill to ban data centers on public landKDRV NewsWatch 12Sep 30, 5:42 PM ET
- Nuclear-powered AI data center proposed on state and federal land in central eastern UtahKSL.comSep 30, 4:53 PM ET
- A startup wants to build a massive nuclear-powered data center on public land in UtahKUERSep 30, 10:10 AM ET
- 9.6GW Project Beehive: $1bn-Backed Nuclear Data Center Construction Planned Across Utah Public LandConstruction ReviewSep 30, 9:34 AM ET
Every headline is the outlet’s own, credited and linked. A headline isn’t an event: five outlets wrote “judge halts data center” over two weeks about one stay. The timeline below says it once, on the day, with the order.
The timeline
October 2026
- Oct 5, 2026 Deadline
Boulder City’s response to BLM’s motion is due
The city opposes the remand and said it will lay out its reasoning in a legal response due October 5.
Interior Board of Land Appeals · Boulder City, Nevada: the first data center approved on BLM land · Nevada · Lake Mead National Recreation Area · Townsite Solar 2 AI Data Center (Boulder City) · Source: Las Vegas Review-Journal
September 2026
- Sep 30, 2026 Vote
Senate Republicans block Wyden’s bill to ban selling public land for data centers
Sen. Ron Wyden introduced a bill to ban the sale or transfer of federal public land for new data centers and their infrastructure, in Oregon and nationwide, and asked the Senate to pass it by unanimous consent. Republicans blocked it. His office ties it to the 12 proposals on more than 17,000 acres and a federal parcel near Hermiston, Oregon.
U.S. Senate · Congress · Source: Office of Sen. Ron Wyden
- Sep 30, 2026 Announcement
Valar Atomics wants 456 reactors and data centers on more than 9,000 acres of BLM land near Price, Utah
NPR reported Valar’s Project Beehive: data centers, some 456 small nuclear reactors, a fuel plant and nuclear waste storage on over 9,000 acres of BLM land, plus about 650 acres of state land, for around 9.6 gigawatts. BLM’s Utah office confirmed the application and is reviewing it for completeness. Valar had earlier dropped a 10,200 acre site near Green River.
Bureau of Land Management · Interior’s list of public land for data centers · Utah · Valar Atomics Project Beehive (BLM near Price) · Source: NPR
- Sep 24, 2026 Withdrawal
A developer withdraws a 1,000 MW data center and gas plant proposed on BLM land at Henderson
Skylar Opportunities, an affiliate of the Skylar Capital company behind the Townsite project, withdrew its application for a data center and gas plant on 680 acres of BLM land near Henderson’s Paradise Hills neighborhood, citing the city’s planned development in the same area.
Bureau of Land Management · Interior’s list of public land for data centers · Nevada · Henderson BLM Hyperscale Data Center (Skylar Capital, Paradise Hills) · Source: Las Vegas Review-Journal
- Sep 24, 2026 Statement
Sixteen House Democrats demand Interior’s plans for data centers on public land
Reps. Jared Huffman and Dina Titus led 14 colleagues in a letter to Interior Secretary Doug Burgum asking about the data center proposals on more than 17,600 acres of public land in six states, which have had no public input.
U.S. House of Representatives · Interior’s list of public land for data centers · Source: Office of Rep. Jared Huffman
- Sep 23, 2026 Statement
Boise’s mayor comes out against the Blacks Creek data center
Mayor Lauren McLean said selling off public land for mega data centers is shortsighted, and that no data center of this size should be considered anywhere until there’s a statewide framework protecting Idahoans and their natural resources.
Mayor of Boise · Blacks Creek, Idaho: 3,200 acres of BLM land south of Boise · Idaho · Rhea Data Blacks Creek Campus (BLM Four Rivers) · Source: City of Boise
- Sep 21, 2026 Announcement
BLM confirms a four million square foot data center and gas plant proposed on 3,200 acres south of Boise
Rhea Data, a subsidiary of Arevia Power of Las Vegas, applied for a multi-building campus near Blacks Creek Reservoir on Kuna-Mora Road, with a natural gas plant, a tie into Idaho Power and rights-of-way reaching into Elmore County. BLM’s Four Rivers Field Office first got the application in August 2025 and puts the footprint at 3,750 acres, a 3,200-acre campus plus 550 acres of transmission. It’s about 5.5 times the size of Meta’s Kuna data center a short drive west. BLM is still asking about water demand and cooling and is holding back the power figure while the design takes shape. The Sierra Club’s Idaho chapter called it unacceptable.
It’s the largest data center on public land yet described in public, it comes with its own gas plant, and the reservoir beside it is a bird reserve that Audubon volunteers spent six years cleaning up.
BLM Four Rivers Field Office · Blacks Creek, Idaho: 3,200 acres of BLM land south of Boise · Idaho · Rhea Data Blacks Creek Campus (BLM Four Rivers) · Source: Idaho Statesman
- Sep 21, 2026 Lawsuit
BLM asks the board to set aside its own approval of the Townsite data center
In a filing Monday, BLM attorney Kathryn Brinton asked the Interior Board of Land Appeals to set aside the agency’s decision approving the right-of-way amendment so it can conduct additional review of the application. The developer, Townsite Solar 2, supports the motion. The Center for Biological Diversity and the Sierra Club took no position. Boulder City opposes it, because a remand would lift the stay without committing BLM to an environmental assessment, public involvement or a cooperating-agency role for the city.
Three weeks after the board found the challengers likely to win, the agency is asking to take back the first data center approval on BLM land rather than defend it. Whatever comes next at Townsite goes through the review the first approval skipped.
Interior Board of Land Appeals · Boulder City, Nevada: the first data center approved on BLM land · Nevada · Lake Mead National Recreation Area · Townsite Solar 2 AI Data Center (Boulder City) · Source: Las Vegas Review-Journal
- Sep 18, 2026 Announcement
BLM is weighing at least 12 data center proposals on 17,600 acres across six states
The Washington Sun read BLM’s right-of-way records and found at least a dozen data center and data center infrastructure proposals on public land in Arizona, Idaho, Nevada, Oregon, Utah and Wyoming, most never reported and several unknown to the local officials the paper called. Four are in Arizona, at least three in Nevada, one each in Idaho and Oregon, and Prometheus Hyperscale wants an access road, a telecom line and a water pipeline in Wyoming. Valar Atomics’ 10,200-acre nuclear-and-data-center site near Green River, Utah was the largest until the company told the Sun after publication that it had dropped it. BLM said each proposal gets a NEPA review with public comment.
Interior’s own parcel list is still secret. This is the first count of what’s in the pipeline, and it’s the count the next approvals will be measured against.
The Washington Sun · Interior’s list of public land for data centers · Source: The Washington Sun
- Sep 17, 2026 Statement
New Mexico’s Democratic nominee for governor promises a data center pause on her first day
Deb Haaland, the former Interior secretary, said she would sign an executive order on taking office halting every new large-scale data center proposal while the Legislature writes rules for them. She named the rules she wants: no non-disclosure agreements, developers building their own renewable power, closed-loop cooling, and decommissioning bonds like the ones the state puts on oil and gas.
The land commissioner has already refused two data centers on state trust land. A governor elected on a pause would put the state’s other lever, permits and incentives, behind the same answer. Both offices are on the November 3 ballot.
New Mexico governor’s race · New Mexico’s state trust land · New Mexico · Source: Source New Mexico
- Sep 17, 2026 Vote
The Senate blocks a fast track for the Ratepayer Protection Act
Sen. Jon Husted asked to pass the House bill by unanimous consent the day after the House vote. Sen. Martin Heinrich objected, saying a bill that only tells states to consider a standard has no teeth, then asked consent for his own GRID Savings Act, which would require large loads to pay for their grid connections. Sen. Bernie Moreno objected to that.
The bill now waits on committee time in the Senate, where the Mount Hood bill has sat since December.
U.S. Senate · Congress · Source: LiveNOW from FOX
- Sep 16, 2026 Bill
Rep. Titus files a bill to end the right-of-way shortcut BLM used at Boulder City
H.R. 10465, the Public Lands Accountability Act, would bar an agency from amending an existing BLM right-of-way to allow a data center without its own environmental review, take data centers out of the categorical exclusions that skip a full review, require BLM to weigh a project’s effect on the regional water supply, and ask developers for a workforce plan with local jobs and wages. It went to the Natural Resources and Agriculture committees.
The Townsite approval rested on a solar right-of-way amended into a data center. This is the first bill written to close that door, and the Center for Biological Diversity opposes it for stopping short of a ban.
U.S. House · Congress · Source: Las Vegas Review-Journal
- Sep 16, 2026 Vote
The House passes the Ratepayer Protection Act 417 to 3
H.R. 9340, from Reps. Gabe Evans and Kathy Castor, passed under suspension of the rules on roll call 312. It would have state utility regulators consider a standard under which customers drawing 100 MW or more pay the full cost of the generation and transmission built to serve them, with financial assurances if a project is canceled or moved. It doesn’t require any state to adopt the standard.
Every Republican present and all but three Democrats voted for it. Who pays for the buildout is the one data center question Congress has now voted on.
U.S. House · Congress · Source: Clerk of the U.S. House, roll call 312
- Sep 14, 2026 Deadline
The comment period on the Houston transfer closes with more than 2,100 comments
Public comment on the preliminary decision ended September 14. The proposal drew over 2,100 comments. A final decision from the Department of Natural Resources comes next.
Alaska ran the public process that the federal path at Townsite skipped, and it produced 2,100 comments on a transfer of land nobody had yet proposed to build on.
Alaska Department of Natural Resources · Alaska’s state land at Houston, in the Mat-Su · Alaska · Source: Alaska Beacon
- Sep 13, 2026 Memo
Interior orders BLM state directors to list public land for data centers, with three days to answer
The Salt Lake Tribune reported that Interior leadership told BLM’s state directors to identify tracts of public land that could take data centers and return their lists within three days, as a top priority. No list has been made public.
The Townsite template, a right-of-way turned into a data center, is what a parcel list would repeat across the West.
Department of the Interior · Interior’s list of public land for data centers · Source: The Salt Lake Tribune
- Sep 9, 2026 Statement
Sen. Wyden comes out against H.R. 655
Senator Ron Wyden said the bill is a fast track to selling off public lands and that Congress should not be in the business of helping sell off Oregon’s natural treasures.
Without Oregon’s senators the transfer is stalled in the Senate.
U.S. Senate · Mount Hood National Forest and Google’s water · Oregon · Mount Hood National Forest · Source: Columbia Riverkeeper
- Sep 9, 2026 Statement
Five Alaska senators question whether the Houston land transfer is legal
Five members of the Senate Resources Committee, Cathy Giessel, Bill Wielechowski, Forrest Dunbar, Matt Claman and Scott Kawasaki, signed letters to the Department of Natural Resources during the comment period. They cite a Legislative Affairs Agency analysis questioning whether the conveyance meets the statutory requirement that state land serve a sufficient public purpose, and say they are not satisfied that the department reviewed the proposed projects or their environmental effects.
The objection is to the giveaway itself rather than to any one data center, which is the argument that reaches the land before a developer does.
Alaska Senate Resources Committee · Alaska’s state land at Houston, in the Mat-Su · Alaska · Source: Alaska Beacon
- Sep 8, 2026 Moratorium
Oregon pauses every data center request on state land through July 2027
Gov. Kotek’s office announced an immediate pause on unapproved requests for easements, rights-of-way, leases, rentals, land-use permits and sales or transfers of state-owned property for data center projects, through July 1, 2027, or until new direction.
The broadest public-land moratorium on data centers by any government so far.
Governor of Oregon · Oregon’s state land · Oregon · Source: Oregon Capital Chronicle
- Sep 3, 2026 Statement
New Mexico’s land commissioner refuses a data center at Spaceport America
Commissioner Garcia Richard said she will not approve the Green Data and Aetherion data center at Spaceport America, on state trust land, while Sierra County’s moratorium remains in effect.
A state landowner deferring to a county moratorium is the reverse of the federal pattern.
New Mexico State Land Office · New Mexico’s state trust land · New Mexico · Source: Source New Mexico
- Sep 1, 2026 Stay
The Interior Board of Land Appeals stays the Townsite approval
Administrative Judge David Gunter stayed BLM’s authorization, finding the appellants likely to prevail on their NEPA claim and that the public interest in fast data center development does not outweigh the review the law requires. Construction is halted while the board hears the appeal.
The first data center on public land is stopped, for now, by the process it skipped.
Interior Board of Land Appeals · Boulder City, Nevada: the first data center approved on BLM land · Nevada · Lake Mead National Recreation Area · Townsite Solar 2 AI Data Center (Boulder City) · Source: Nevada Current
August 2026
- Aug 27, 2026 Ruling
The Cave City data center suits proceed
The court let the suits over the moratorium and the annexation go forward.
Barren Circuit Court · Cave City, Kentucky, beside Mammoth Cave · Kentucky · Mammoth Cave National Park · Cave Point Commerce Center · Source: Bowling Green Daily News
July 2026
- Jul 30, 2026 Order
Gov. Kotek kills a state land sale to a Google-funded data center developer in Salem
Oregon Gov. Tina Kotek directed the Department of Administrative Services to terminate a pending contract to sell 32 acres of state-owned land at the Mill Creek Corporate Center to Verrus, a California company funded by Google, for a 75-acre data center.
The first governor to block a data center on state land outright.
Governor of Oregon · Oregon’s state land · Oregon · Source: Salem Reporter
- Jul 29, 2026 Award
DOE awards Paducah to Brookfield and NextEra: 1.8 GW, 2 GW of new gas, over $100 billion
Brookfield will develop and operate a 1.8 gigawatt AI and high-performance computing campus on the former uranium enrichment site in western Kentucky; NextEra Energy will build 2 gigawatts of gas generation and up to 2.6 gigawatts of storage. Construction is expected through 2031.
The first federal site to get a developer, and the largest single announcement in the fight so far.
Department of Energy · The Energy Department’s federal sites · Kentucky · DOE Paducah AI Infrastructure Site · Source: U.S. Department of Energy
- Jul 27, 2026 Lawsuit
Conservation groups and Boulder City residents appeal the Townsite approval
The Center for Biological Diversity and the Sierra Club Toiyabe Chapter filed an administrative appeal at the Interior Board of Land Appeals, arguing BLM approved the data center without the site-specific environmental review the National Environmental Policy Act requires and without public comment.
The appeal is the first legal test of a data center on public land.
Interior Board of Land Appeals · Boulder City, Nevada: the first data center approved on BLM land · Nevada · Lake Mead National Recreation Area · Townsite Solar 2 AI Data Center (Boulder City) · Source: Center for Biological Diversity
- Jul 23, 2026 Bill
Rep. Tlaib introduces the No AI Data Centers on Federal Lands Act
H.R. 9939 would permanently bar large AI data centers and their infrastructure on federally owned or managed land, including military bases, and require existing ones removed and their sites remediated. Five cosponsors; referred to the House Natural Resources Committee.
The first bill to answer the executive order directly.
U.S. House · Congress · Source: Congress.gov
- Jul 22, 2026 Moratorium
Sierra County, New Mexico adopts a data center moratorium as residents protest the Spaceport proposal
The county commission approved a moratorium on data centers while residents opposed a proposed campus at Spaceport America, which sits on leased state trust land.
One of several New Mexico counties to freeze data centers this year.
Sierra County · New Mexico’s state trust land · New Mexico · Source: Source New Mexico
- Jul 16, 2026 Order
New Mexico’s land commissioner blocks a Project Jupiter pipeline from state trust land
Commissioner of Public Lands Stephanie Garcia Richard refused a pipeline tied to the Project Jupiter data center from crossing state trust land.
State trust land is a lever a single elected official can pull.
New Mexico State Land Office · New Mexico’s state trust land · New Mexico · Source: Source New Mexico
- Jul 16, 2026 Announcement
Alaska moves to hand 20,000 acres near Houston to its own development authority
The Department of Natural Resources issued a preliminary decision in July to convey nearly 20,000 acres of state land, about 30 square miles near Houston in the Matanuska-Susitna Borough, to the Alaska Industrial Development and Export Authority. The transfer is non-competitive and costs AIDEA nothing. The stated purpose is a multi-use industrial and energy development district, and data centers are one of the uses named for it.
A state agency conveying public land to a state authority at no cost, with nobody else allowed to bid, is the cleanest version of the pattern this page tracks: the land moves before any project is named, so the project never faces the land decision.
Alaska Department of Natural Resources · Alaska’s state land at Houston, in the Mat-Su · Alaska · Source: Alaska Beacon
- Jul 15, 2026 Hearing
Senate subcommittee holds a hearing on H.R. 655
The Senate Energy and Natural Resources Subcommittee on Public Lands, Forests, and Mining held a hearing on the bill.
The bill was moving in the Senate until Oregon’s senior senator came out against it.
U.S. Senate · Mount Hood National Forest and Google’s water · Oregon · Mount Hood National Forest · Source: Congress.gov
- Jul 7, 2026 Lawsuit
A second suit seeks to void the annexation tied to the Cave City data center
A second lawsuit asked the court to void the city annexation connected to the proposed campus, as Cave City moved to dismiss the developer’s first suit.
Barren Circuit Court · Cave City, Kentucky, beside Mammoth Cave · Kentucky · Mammoth Cave National Park · Cave Point Commerce Center · Source: WCLU Radio
June 2026
- Jun 26, 2026 Approval
BLM approves the first data center on BLM land, 88.5 acres in Boulder City, Nevada
The Bureau of Land Management approved construction of the Townsite Data Center on 88.5 acres of public land in Eldorado Valley, next to the Townsite Solar project, citing Executive Order 14318. The developer had pulled the same project from Boulder City’s own land process after residents objected.
The first data center ever approved on BLM land, cleared without a new environmental review by treating it as a change to a solar right-of-way.
Bureau of Land Management · Boulder City, Nevada: the first data center approved on BLM land · Nevada · Lake Mead National Recreation Area · Townsite Solar 2 AI Data Center (Boulder City) · Source: Bureau of Land Management
- Jun 8, 2026 Lawsuit
Kentucky Industrial Alliance sues Cave City over the moratorium
The developer sued the city, its council and the Barren County joint planning commission in Barren Circuit Court, asking a judge to declare the moratorium unlawful and to have its application reviewed under the rules in place on May 11, the day it filed.
The moratorium is the tool that is working against data centers, and it is now the tool being litigated.
Barren Circuit Court · Cave City, Kentucky, beside Mammoth Cave · Kentucky · Mammoth Cave National Park · Cave Point Commerce Center · Source: WBKO
- Jun 3, 2026 Announcement
BLM tells Umatilla County it holds a data center application on public land outside Hermiston
At the county board's June 3 meeting, BLM Baker Field Manager Sarah Sherman briefed the commissioners on current projects and said the bureau had received an application for a proposed data center outside Hermiston. The minutes name no applicant, acreage or capacity. The Washington Sun's September read of BLM right-of-way records lists one Oregon data center application, by Copia Power.
This is the Oregon application in the queue that Sen. Wyden's office is writing to Interior about, on the county record three months before any newspaper had it. The site would sit in the Hermiston cluster, about seven miles from Cold Springs National Wildlife Refuge.
Umatilla County Board of Commissioners · Interior’s list of public land for data centers · Oregon · Undisclosed BLM Data Center Project (Hermiston) · Source: Umatilla County Board of Commissioners, minutes of June 3, 2026
May 2026
- May 20, 2026 Moratorium
Cave City, Kentucky freezes data centers for twelve months, nine days after a 1.2 GW campus was filed
After two special meetings on May 18 and May 20 the Cave City council adopted a twelve-month moratorium on data centers. Kentucky Industrial Alliance had filed plans on May 11 for a campus of about 380 acres on Doyle Avenue, north of downtown and a few miles from Mammoth Cave National Park.
A town of 2,500 beside a national park used the one tool a town has, and the developer went to court over it within three weeks.
Cave City council · Cave City, Kentucky, beside Mammoth Cave · Kentucky · Mammoth Cave National Park · Cave Point Commerce Center · Source: WBKO
December 2025
- Dec 9, 2025 Vote
The House passes H.R. 655
After forty minutes of debate the House passed the Dalles Watershed Development Act and sent it to the Senate.
A public-land transfer for data center water cleared one chamber with little notice.
U.S. House · Mount Hood National Forest and Google’s water · Oregon · Mount Hood National Forest · Google The Dalles Campus C3 · Source: Congress.gov
July 2025
- Jul 24, 2025 Announcement
DOE picks four sites: Idaho National Laboratory, Oak Ridge, Paducah, Savannah River
Of the 16 sites, Secretary Wright selected four for private developers to build and power AI data centers, and DOE followed with solicitations at each through the fall of 2025.
Four Cold War reservations with their own transmission became the federal government’s data center inventory, with no county vote and no zoning hearing.
Department of Energy · The Energy Department’s federal sites · Savannah River Site IT · Source: U.S. Department of Energy
- Jul 23, 2025 Order
The White House orders federal land opened to data centers
Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure, directs federal agencies to make federally owned land and resources available for data center development and to speed the permits. Every federal approval since cites it.
This is the order behind the BLM approval in Nevada, the DOE site awards and Interior’s parcel list. The fight over data centers on public land starts here.
White House · The White House order · Source: The White House
April 2025
- Apr 3, 2025 Solicitation
DOE names 16 federal sites for AI data centers
The Energy Department issued a request for information on building AI data centers and the power to run them at 16 of its sites, with a target of operations by the end of 2027.
The first federal offer of land for the buildout, months before the executive order.
Department of Energy · The Energy Department’s federal sites · Source: U.S. Department of Energy
January 2025
- Jan 23, 2025 Bill
H.R. 655 would hand 150 acres of Mount Hood National Forest to The Dalles
Rep. Cliff Bentz introduced the Dalles Watershed Development Act, directing the Forest Service to convey about 150 acres of the Mount Hood National Forest to the City of The Dalles, Oregon, at no cost, for the city’s water system. The water demand is the city’s data centers, led by Google’s campus.
The first bill to move national forest land for a data center was about the water, not the building.
U.S. House · Mount Hood National Forest and Google’s water · Oregon · Mount Hood National Forest · Google The Dalles Campus C3 · Source: Congress.gov
In Congress
read 51 minutes ago from Congress.gov · every bill naming a data center, plus H.R. 655 and H.R. 9939 by number
- Ratepayer Protection ActSep 30, 2026 · Motion to proceed to consideration of measure withdrawn in Senate. (CR S5199)H.R. 9340
- Reverse Big Ugly Tax Breaks for Data Centers ActSep 16, 2026 · Referred to the House Committee on Ways and Means.H.R. 10448
- Public Lands Accountability ActSep 16, 2026 · Referred to the Committee on Natural Resources, and in addition to the Committee on Agriculture, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.H.R. 10465
- A bill to amend the Internal Revenue Code of 1986 to exclude data centers from the definition of qualified opportunity zone businesses.Sep 16, 2026 · Read twice and referred to the Committee on Finance.S. 5418
- Data Center Fairness Fee Act of 2026Sep 16, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 10467
- Responsible Data Center Siting Act of 2026Sep 8, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 10321
- Data Center Fair Share ActSep 8, 2026 · Referred to the Committee on Energy and Commerce, and in addition to the Committee on Transportation and Infrastructure, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.H.R. 10322
- To prohibit the provision of Federal financial benefit for the construction, expansion, or substantial rehabilitation of data centers on prime farmland and other certain farmland.Aug 27, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 10169
- No Data Center NDAs ActAug 20, 2026 · Referred to the House Committee on House Administration.H.R. 10118
- Protecting Local Control of Data Centers ActAug 20, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 10119
- Data Center Community Reinvestment Act of 2026Aug 13, 2026 · Referred to the Committee on Ways and Means, and in addition to the Committees on Energy and Commerce, and Science, Space, and Technology, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.H.R. 10102
- Expressing the sense of the House of Representatives that every American and community impacted by the construction or operation of an artificial intelligence data center should have the right to transparency and local autonomy.Aug 3, 2026 · Referred to the Committee on Energy and Commerce, and in addition to the Committee on the Judiciary, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.H.Res. 1471
- Smart Data Center Policy ActAug 3, 2026 · Referred to the Committee on Transportation and Infrastructure, and in addition to the Committees on Armed Services, and Energy and Commerce, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.H.R. 10041
- Data Center Resource Disclosure ActJul 30, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 10005
- No AI Data Centers on Federal Lands ActJul 23, 2026 · Referred to the House Committee on Natural Resources.H.R. 9939
- Data Center Water and Energy Transparency Act of 2026Jul 22, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 9825
- Protecting Families from AI Data Center Energy Costs ActJul 21, 2026 · Ordered to be Reported by the Yeas and Nays: 44 - 0.H.R. 6529
- Data Center Tax Accountability and Disclosure Act of 2026Jul 21, 2026 · Read twice and referred to the Committee on Finance.S. 5054
- Dalles Watershed Development ActJul 15, 2026 · Committee on Energy and Natural Resources Subcommittee on Public Lands, Forests, and Mining. Hearings held.H.R. 655
- Protecting Communities from Data Center Impacts Act of 2026Jul 9, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 9629
- Artificial Intelligence Data Center Moratorium ActJun 24, 2026 · Referred to the Committee on Energy and Commerce, and in addition to the Committee on Foreign Affairs, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.H.R. 9442
- AI Data Center Site Selection Transparency Act of 2026Apr 23, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 8488
- A concurrent resolution expressing the sense of Congress that the Ratepayer Protection Pledge announced on March 4, 2026, reflects sound national policy to protect ratepayers in the United States, promote electricity affordability, and ensure that all people of the United States, including households, small businesses, schools, hospitals, and farms, have access to reliable and affordable energy as artificial intelligence and data center infrastructure expands across the United States.Mar 25, 2026 · Referred to the Committee on Energy and Natural Resources. (text: CR S1618-1619)SCONRES 30
- Artificial Intelligence Data Center Moratorium ActMar 25, 2026 · Read twice and referred to the Committee on Commerce, Science, and Transportation.S. 4214
- Data Center Water and Energy Transparency Act of 2026Mar 25, 2026 · Read twice and referred to the Committee on Energy and Natural Resources. (text: CR S1616-1617)S. 4213
- No Harm Data Centers ActMar 20, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 8033
- Data Center Community Impact ActMar 5, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 7858
- Data Center Transparency ActJan 8, 2026 · Referred to the House Committee on Energy and Commerce.H.R. 6984
In the Federal Register
read 14 hours ago · notices from Interior, BLM, the Forest Service, the Park Service, Fish and Wildlife or DOE that name a data center, last twelve months
None. No notice from those agencies has named a data center in the last twelve months. That’s the point: the Townsite approval went through without one, which is what the appeal is about.
Local fights
Attend the Planning Commission Public Hearing to Oppose the Edsall Data Center Substation
Next meeting Wed, Dec 2, 7:30 PM ET, Fairfax County Government Center Auditorium, 12000 Government Center Parkway, Fairfax, VA 22035 · the noticesites.google.com
Add to the record
An update on any fight above, with its source, or a group working on one. It goes on the page the moment the link checks, labeled as a reader’s report.
Share this page
Watch this fight
Alerts for any ZIP code cover a place. Leave the ZIP blank and you get the national record: every data center that lands, breaks ground or is stopped, anywhere.
How this page is kept
The headlines are read from the outlets every fifteen minutes and shown as written. The timeline is ours: one entry per event, dated to the day it happened, with the primary document where one exists (the BLM decision, the appeals board order, the governor’s directive, the bill) and the outlet that reported it where one doesn’t. Bills come from Congress.gov daily. Federal Register notices come from the Register daily. If we’ve missed an event or gotten one wrong, write to ask@morethanjustparks.com with the source.