Comments closed November 4
Burns District BLM would add 10 herbicides and drone spraying
Bureau of Land Management · Burns District, Andrews Field Office
- What
- BLM wants to add up to 10 herbicides and drone spraying to the Burns District's invasive plant program in southeastern Oregon, which has treated an average of 57,260 acres a year over the past decade.
- Where
- Burns District, Andrews Field Office, OR
- How much
- Total BLM acres managed by Burns District: approximately 3.3 million acres. Average annual acres treated over last 10 years: 57,260 acres per year average. Invasive annual grass estimated acres in WSAs: 684,596 acres.
- Decided
- Comments closed November 4, 2026. No decision document is on file yet.Date from BLM ePlanning project page ↗, read October 28, 2026.
Where these four lines come from
- WhatOur plain-English read of the BLM NEPA Register DOI-BLM-ORWA-B060-2026-0001-EA ↗. Check it against the agency’s own words under Case.
- WhereThe places and states the notice names, as PLAN read them.
- approximately 3.3 million acres“The Burns District manages approximately 3.3 million acres of Bureau of Land Management (BLM)-administered lands in southeast Oregon.” Chapter 1, Introduction Open the document ↗
- 57,260 acres per year average“Over the past 10 years, the District has treated on average 57,260 acres of invasive plants each year: 39,421 acres with herbicide and 17,838 acres with non-herbicide control methods.” Chapter 1, Introduction Open the document ↗
- 684,596 acres“Invasive annual grasses have been estimated at 684,596 acres, based on the best information available at this time.” Issue 3, Affected Environment, Table 3-6 Open the document ↗
- DecidedNovember 4, 2026, from BLM ePlanning project page, its public participation period ↗. Read October 28, 2026. The decision document is the one on file in PLAN’s record.
- Read from PLAN’s record November 13, 2026.
What the proposal said, and what the decision did
No figure from the proposal has been checked against the decision on this fight yet. What the record does hold is the issues ledger below.
No decision document is on PLAN’s record for this fight yet. When the agency’s decision lands, what it answered goes here.
Affects public lands
BLM wants to add up to 10 herbicides and drone spraying to the Burns District's invasive plant program in southeastern Oregon, which has treated an average of 57,260 acres a year over the past decade.
What’s at risk
If this goes through
Our plain-English read of the official notice ↗. Check it against the agency’s own words below.
By the numbers, from the agency’s own document
- Total BLM acres managed by Burns District
Chapter 1, Introduction
Open the document ↗“The Burns District manages approximately 3.3 million acres of Bureau of Land Management (BLM)-administered lands in southeast Oregon.”
- Average annual acres treated over last 10 years
Chapter 1, Introduction
Open the document ↗“Over the past 10 years, the District has treated on average 57,260 acres of invasive plants each year: 39,421 acres with herbicide and 17,838 acres with non-herbicide control methods.”
- Invasive annual grass estimated acres in WSAs
Issue 3, Affected Environment, Table 3-6
Open the document ↗“Invasive annual grasses have been estimated at 684,596 acres, based on the best information available at this time.”
- Total Wilderness Study Area acres on Burns District
Issue 3, Affected Environment, Table 3-4
Open the document ↗“The Burns District administers a total of 684,608 acres within WSAs.”
Source: the agency’s document ↗
The agency’s own analysis
What the notice says, and what it leaves out
The window has closed; the record of what was missing stays.
Chapter 2, Alternatives Considered but Eliminated from Detailed Study ↗
The agency says
“This alternative would remove one or more herbicides from consideration under Alternative 2 for various reasons, including stated risks or apparent lack of need.”
The EA bundles 10 new herbicides into a single up-or-down decision rather than analyzing them individually or in subsets.
Chapter 4, Endangered Species Act ↗
The agency says
“The BLM is in the process of preparing a biological assessment. The BLM will consult with USFWS to address IIPM activities proposed under Alternative 2.”
The EA defers the Endangered Species Act Section 7 consultation to a future biological assessment that has not been completed, yet the document simultaneously proposes to authorize treatments within 300 meters of listed species and critical habitat.
The agency says
“Treatment Plans are an implementation tool and do not require additional site-specific NEPA analyses or decisions.”
The EA tiers to four national and state-level EISs for its herbicide effects analysis but acknowledges that effects from herbicide applications depend on site-specific factors including slope, soil properties, vegetation cover, precipitation, hydrology, and depth to groundwater.
The agency says
“Tribes gather plants in confidential locations, so the BLM would not know whether these resources may be affected until Tribes review the Treatment Plans during government-to-government consultation.”
The EA identifies 72 invasive plant species under its program and analyzes effects for species groups in bulk, but the Tribal consultation section acknowledges that Tribes gather plants in confidential locations and that the BLM would not know whether resources may be affected until Tribes review Treatment Plans during government-to-government consultation.
In the agency’s own words
The District is proposing to update and expand this program by: • Adding 10 additional herbicide active ingredients (aminocyclopyrachlor, aminopyralid, clethodim, fluazifop-P-butyl, flumioxazin, fluroxypyr, imazamox, indaziflam, oryzalin, and rimsulfuron) to the list of herbicides available for use on the Burns District for invasive plant management; • Including the use of new technology such as drones for aerial applications and monitoring; and • Updating the proposed treatment acres from the existing Burns Integrated Invasive Plant Management EA to include the areas on which the new herbicides would be used in…
Who signs it
The notice names no signer PLAN could read. PLAN names a decision-maker only when the document names one.
The ground
The window has closed, so there’s no watch to set on it here.
The photograph on this page: Greater sage-grouse displaying on a lek in sagebrush country. It’s the country this decision sits in, not the site itself. More Than Just Parks.
In court on this ground
No court case we track is over Burns Andrews Field Office and Burns Three Rivers Field Office.
Who holds the vote
PLAN’s record doesn’t tie a member of Congress to this fight yet. The scorecard grades the votes and bills that decide public lands; nothing joins a vote or a bill to this decision, so there’s no member to name here without guessing.
See how your members vote ↗BLM ePlanningWe track this on the agency’s own system of record, where most on-the-ground decisions live.
On the record for this fight
3 people told us they filed on this fight through PLAN; we haven’t found any of their letters on the agency’s record yet.
- Angeline58 seals
- Amy M.59 seals
- and 1 more steward
Ranked on letters found on the agency’s record, then letters filed. Readers appear as first name and last initial, or as a steward in their state; switch yours off in your record. All boards
Know an open comment period we are missing, or spotted a wrong deadline? .
More fights that need you
Go deeper for free
See how your members of Congress vote on public lands
Every representative, graded on the votes that decide the fate of parks, forests, and refuges.
Open ↗The mapSee the places under active threat
A live map of the parks, monuments, and wild country in the crosshairs right now.
Open ↗A wrong fact, a dead link, a form that wouldn’t take your letter: one tap and it comes to the people who build PLAN, with this fight attached.