Demand Answers Before Graphite Creek Buries 389 Acres of Alaska Wetlands
U.S. Army Corps of Engineers · Graphite Creek watershed, Alaska wetlands and waters associated with the Graphite Creek mining area
- What
- The proposed open-pit mine would permanently fill 389.8 acres of Alaska wetlands and waters and divert 12,440 linear feet of streams over a 21-year mine life, with a record of decision planned roughly one year after this scoping notice.
- Where
- Graphite Creek watershed, Alaska wetlands and waters associated with the Graphite Creek mining area, AK
- How much
- Permanent wetland and water fill: 389.8 acres. Total project footprint: 1,176.0 acres. New gravel access road length: 17.3 miles.
- Decided
- Comments closed November 2, 2026. No decision document is on file yet.Date from Army Corps public notice (Regulatory Request System) ↗, read September 30, 2026.
Where these four lines come from
- WhatOur plain-English read of the Army Corps public notice ↗. Check it against the agency’s own words under Case.
- WhereThe places and states the notice names, as PLAN read them.
- 389.8 acres“permanently discharge fill material into 389.8 acres of waters including wetlands” PROJECT DESCRIPTION Open the document ↗
- 1,176.0 acres“within the 1,176.0-acre footprint of the Project, which includes the mine, the proposed access road” PROJECT DESCRIPTION Open the document ↗
- 17.3 miles“The project site, including the mine site and the 17.3-mile access road, is located” LOCATION Open the document ↗
- DecidedNovember 2, 2026, from Army Corps public notice (Regulatory Request System), its comment end date ↗. Read September 30, 2026. The decision document is the one on file in PLAN’s record.
- Read from PLAN’s record November 15, 2026.
What the proposal said, and what the decision did
No figure from the proposal has been checked against the decision on this fight yet. What the record does hold is the issues ledger below.
No decision document is on PLAN’s record for this fight yet. When the agency’s decision lands, what it answered goes here.
PLAN's read: critical threat
The proposed open-pit mine would permanently fill 389.8 acres of Alaska wetlands and waters and divert 12,440 linear feet of streams over a 21-year mine life, with a record of decision planned roughly one year after this scoping notice.
What’s at risk
If this goes through
Our plain-English read of the official notice ↗. Check it against the agency’s own words below.
By the numbers, from the agency’s own document
- Permanent wetland and water fill
PROJECT DESCRIPTION
Open the document ↗“permanently discharge fill material into 389.8 acres of waters including wetlands”
- Total project footprint
PROJECT DESCRIPTION
Open the document ↗“within the 1,176.0-acre footprint of the Project, which includes the mine, the proposed access road”
- New gravel access road length
LOCATION
Open the document ↗“The project site, including the mine site and the 17.3-mile access road, is located”
- Stream length diverted from natural channel
PROJECT DESCRIPTION
Open the document ↗“the diversion of 12,440 linear feet of stream into artificially constructed channels”
- Anticipated mine operating life
- Temporary jurisdictional water impacts
PROJECT DESCRIPTION
Open the document ↗“also incur temporary impacts to 142.6 acres of jurisdictional waters”
Source: the agency’s document ↗
Testing the agency’s case
What the agency argues, and whether its own record backs it
- 2
- Hold up
- 5
- Not fully backed
The Army Corps of Engineers will prepare an environmental impact statement before it decides whether to issue a Section 404 fill permit for Graphite One's open pit graphite mine and 17.3-mile access road north of Nome. It says the review is needed because the project would have significant impacts on aquatic resources, water quality, fish and wildlife, subsistence and the regional economy.
“USACE has determined that the Project would have significant impacts to aquatic resources as well as to the local/regional economy and society, aesthetics and cultural importance, water quality, fish and wildlife, and subsistence.”
Project Background
Purpose and needNot fully backedThe mine would provide essential supply-chain infrastructure for the United States' renewable energy, storage and defense sectors.
The notice cites total import dependence, federal critical mineral designations and a World Bank projection that demand will rise 383 percent between 2020 and 2050. But the concentrate would be shipped out of Alaska for further processing at a place the notice doesn't name. The notice gives no annual output either, so it doesn't show the link to a domestic supply chain.
The agency’s words, the record +Hide the words
The agency says
“As a result, the Project would provide essential supply-chain infrastructure for the United States’s renewable energy sector and storage systems, as well as advanced graphite materials for industrial and Defense Industrial Base applications.”
Purpose and Need
Elsewhere in the same document
“The ore concentrate would be shipped out of Alaska for further processing and manufacturing of Coated Spherical Graphite, which would supply material needed for electric vehicle lithium-ion batteries and energy storage as well as other high-grade graphite products.”
Project Description
EffectsNot fully backedImpacts to 142.6 acres of waters, including 12,440 linear feet of stream moved into built channels, would be temporary.
The notice labels these impacts temporary and says the diverted flow would still reach Graphite Creek downstream. It never says how long the diversions would last, whether the streams would go back to their old channels, or how. Mining runs through closure in Year 21, and the notice includes no restoration plan.
The agency’s words, the record +Hide the words
The agency says
“The Project would also incur temporary impacts to 142.6 acres of jurisdictional waters including the diversion of 12,440 linear feet of stream into artificially constructed channels that would convey flow into Graphite Creek downstream of the mine site.”
Project Description
Elsewhere in the same document
“Phase 1 would occur within the first 5 years; Phase 2 would occur from Years 6 through 12; Phase 3 would occur from Years 13 through closure, which is anticipated to occur in Year 21.”
Project Description
EffectsNot fully backedApart from the Port of Nome expansion, no other major industrial actions are proposed or ongoing anywhere on the Seward Peninsula.
The Corps gives this statement as context for its finding of significant impacts. It sits next to the point that the mine would be the only large mine operating on the Seward Peninsula. The notice gives no list, source or survey for the statement. The standard scoping request for information on nearby activities doesn't by itself show the statement is wrong.
The agency’s words, the record +Hide the words
The agency says
“Except for the expansion of the Port of Nome, there are no other major industrial actions proposed or ongoing in the entire Seward Peninsula.”
Project Background
Elsewhere in the same document
“Graphite One has assumed that the Port of Nome expansion project would have progressed sufficiently to allow self-loading container ships to load containers dockside.”
Project Description
Show 2 more claims +Show fewer
EffectsNot fully backedThe project may affect, but isn't likely to adversely affect, species listed under the Endangered Species Act.
Both consulting agencies formally agreed with the Corps' determination: the U.S. Fish and Wildlife Service on April 16, 2026 and the National Marine Fisheries Service on August 7, 2026. The notice doesn't name the species or include the analysis. Still, the claim reports the agencies' recorded conclusions. The Corps' later finding of significant fish and wildlife impacts covers wildlife broadly and doesn't conflict with a finding limited to listed species.
The agency’s words, the record and the law +Hide the words
The agency says
“On April 16, 2026, the U.S. Fish and Wildlife Service (USFWS) concurred with the USACE determination that the Project may affect and is not likely to adversely affect listed and candidate species under the Endangered Species Act managed by USFWS.”
Project Background
Elsewhere in the same document
“On August 7, 2026, NMFS concurred with the USACE determination that the Project may affect and is not likely to adversely affect listed and candidate species under the Endangered Species Act managed by NMFS.”
Project Background
The law
“Each Federal agency shall, in consultation with and with the assistance of the Secretary, insure that any action authorized, funded, or carried out by such agency (hereinafter in this section referred to as an "agency action") is not likely to jeopardize the continued existence of any endangered species or threatened species” Endangered Species Act, 16 U.S.C. 1536(a)(2) ↗
ProcessNot fully backedTwo scoping meetings, one in person in Nome and one virtual, make it convenient for the public to give input.
The notice offers written, email, mail and virtual options. It also invites the tribes, Native corporations and city governments of Teller and Brevig Mission to act as cooperating agencies. But the only in-person scoping meeting is in Nome. The notice names Teller and Brevig Mission as communities to analyze in depth, and the Corps held meetings in both villages during the earlier review. It doesn't explain why neither village gets a scoping meeting.
The agency’s words, the record +Hide the words
The agency says
“USACE intends to hold two public scoping meetings to make it convenient for the public to provide input into this process.”
Scoping
Elsewhere in the same document
“Additional public comments were provided during public meetings held Nome, Brevig Mission and Teller in mid-April 2026.”
Project Background
“These issues include, but are not limited to, the construction and operation of the facilities and their effect upon subsistence, cultural resources, socioeconomics, fish and wildlife, hydrology and wetlands, and the communities of Teller, Brevig Mission, and Nome.”
Evaluation Factors
Where its own record backs the agency
AuthorityThe Corps decides this permit because the project would permanently fill 389.8 acres of waters and wetlands confirmed as jurisdictional.Why it holds +
The notice ties the permit to the action. Graphite One applied for a Section 404 permit to discharge fill into waters of the U.S., and an approved jurisdictional determination found the affected waters and wetlands jurisdictional. The Authority section marks discharge of dredged or fill material as the basis for the decision.
The agency says
“The Project would permanently discharge fill material into 389.8 acres of waters including wetlands that were determined as jurisdictional via an approved jurisdictional determination completed on July 22, 2026.”
Project Description
Its own record backs it
“Graphite One submitted a Section 404 permit to USACE on August 15, 2025, to allow for the discharge of fill within waters of the U.S. necessary to construct the Project.”
Project Background
ScienceGraphite is a federally designated critical mineral that the United States currently imports entirely.Why it holds +
The notice attributes graphite's status to named federal sources: the Department of Energy's Critical Materials List and the Interior Department's criticality indicators. It also says the country is 100 percent import-dependent for natural graphite. Nothing else in the notice conflicts with these attributed designations.
The agency says
“The U.S. Department of Interior considers graphite to be one of nine critical minerals that meets all six of its industrial/defense sector criticality indicators.”
Purpose and Need
Its own record backs it
“At present, the United States is 100 percent import-dependent for natural graphite.”
Purpose and Need
How this was read
Read from the agency’s own notice ↗, all 8 pages. Every quote is checked word for word against it, a claim marked contradicted stands on a quote from the same document, and a second reading argued the agency’s side of every verdict before it was published. The verdicts are our reading; the quotes are the agency’s. A court can set aside agency action it finds “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law” (5 U.S.C. 706(2)(A) ↗), which is why these gaps are worth putting in the record.
In the agency’s own words
Special Public Notice announcing Notice of Intent to Prepare an EIS
Who signs it
The notice names no signer PLAN could read. PLAN names a decision-maker only when the document names one.
The ground
The window has closed, so there’s no watch to set on it here.
The photograph on this page: Moose in a summer wildflower meadow. It’s the country this decision sits in, not the site itself. More Than Just Parks.
In court on this ground
This fight isn’t bound to a land unit in PLAN’s record yet, so there are no court cases to show for its ground.
Who holds the vote
PLAN’s record doesn’t tie a member of Congress to this fight yet. The scorecard grades the votes and bills that decide public lands; nothing joins a vote or a bill to this decision, so there’s no member to name here without guessing.
See how your members vote ↗Army CorpsWe track this on the agency’s own system of record, where most on-the-ground decisions live.
On the record for this fight
7 people told us they filed on this fight through PLAN; we haven’t found any of their letters on the agency’s record yet.
- Milton M.38 seals
- Angeline58 seals
- Amy M.59 seals
- and 4 more stewards
Ranked on letters found on the agency’s record, then letters filed. Readers appear as first name and last initial, or as a steward in their state; switch yours off in your record. All boards
Know an open comment period we are missing, or spotted a wrong deadline? .
More fights that need you
Go deeper for free
See how your members of Congress vote on public lands
Every representative, graded on the votes that decide the fate of parks, forests, and refuges.
Open ↗The mapSee the places under active threat
A live map of the parks, monuments, and wild country in the crosshairs right now.
Open ↗A wrong fact, a dead link, a form that wouldn’t take your letter: one tap and it comes to the people who build PLAN, with this fight attached.