14 days left
Dall sheep ram above the valley, Denali National Park, Alaska

Open for comment · closes November 14

Approve pedestrian bridge over Nenana River floodplain before scour analysis is complete

Dall sheep ram above the valley, Denali National Park, AlaskaMore Than Just Parks
What
The scour spreadsheet calculates up to 6.70 feet of pier scour under the standard equation but the document reports only 0.4 feet, a 17-fold difference that is never resolved.
Where
Denali National Park and Preserve, Nenana River, AK
By when
Comments to National Park Service by November 14, 2026.Date from National Park Service PEPC project page ↗, read October 31, 2026.

What to ask forAll 7 points →

The agency should supplement the hydraulic report with an explicit uncertainty analysis of the regression-derived discharges and explain how the design accounts for the upper bound of that uncertainty.

Where these four lines come from
Now make it count14 days left

Two ways to be heard on this, and both count. Comment for the legal record, then call the members who answer to you.

Comment now

7 holes in the agency’s own analysis

Make these points, in your own words

  • The document admits the site is unmapped by FEMA and that no stream flow data is available at the crossing, yet it relies entirely on USGS regression equations for an ungaged basin to derive peak discharges.Read the point +

    Regression equations carry substantial uncertainty bands that are not disclosed anywhere in the document. Section 3.1 states 'No stream flow data is available for the river near the crossing site,' but the document never quantifies the uncertainty range around the regression-derived peak discharges in Table 1, never evaluates how that uncertainty propagates into the scour and water-surface-elevation results, and never explains why the regression method is adequate given the glacial, ice-jam-prone character of the river. The agency should supplement the hydraulic report with an explicit uncertainty analysis of the regression-derived discharges and explain how the design accounts for the upper bound of that uncertainty.

  • The scour calculations in Appendix B show that the standard HEC-18 pier scour equation (equation 7.3) produces scour depths of 5.22 feet for the 100-year event and 6.70 feet for the 500-year event, yet Table 3 in the main body reports pier scour of only 0.2 feet and 0.4 feet, respectively, citing the coarse-bed equation (equation 7.34).Read the point +

    The document justifies the coarse-bed equation solely because D50 exceeds 0.8 inches, but it never explains why armoring will be maintained during the extraordinary ice-jam and debris conditions the document itself describes at length, conditions that are known to strip armor and expose finer substrate. The agency should provide a written justification for rejecting the standard equation results and demonstrate that armor will not be disrupted by the ice-jam forces it already acknowledges.

  • The document describes ice jams that can reach 6 feet in height, layered ice sheets 3 to 4 feet thick, and abrasion on the existing highway bridge piers that extends 'up to the top of the casing (and possibly above),' suggesting ice forces may already reach the 100-year flood elevation.Read the point +

    Despite this, the flood risk analysis in Section 3.2 dismisses public safety risk by saying 'water levels typically rise slowly over the course of hours or days,' without addressing the sudden, unpredictable nature of ice-jam releases. The document never models ice-jam surge elevations or quantifies warning time for ice-jam break events. The agency should conduct or commission an ice-jam flood hazard analysis specific to this site and incorporate the results before finalizing the design.

  • The document states that 'geotechnical borings did not indicate bedrock near the streambed surface,' meaning the piers will be founded in unconsolidated alluvial or glacial material, yet the long-term degradation value in Table 3 is listed as 6.0 feet for both the 100-year and 500-year events.Read the point +

    The document never explains the basis for that 6.0-foot long-term degradation estimate or whether a geotechnical report was completed and reviewed. Appendix B shows the abutment scour section of the HEC-18 spreadsheet is entirely blank, with every output showing either zero or a division error, meaning abutment scour was not calculated. The agency should complete the abutment scour analysis and provide the geotechnical report that supports the long-term degradation assumption.

  • The document acknowledges that 'bank erosion and lateral shift of the channel thalweg on the north side of the river is expected to naturally occur over the life span of the new bridge' and that the north abutment has been set back approximately 15 feet from the steep bank face.Read the point +

    However, it never states the expected rate of lateral bank retreat, never defines the design life of the bridge, and never quantifies whether 15 feet of setback is sufficient for the anticipated migration over that design life. The north bank is described as a 50-foot bluff of sandy lean clay subject to undercutting and slumping. The agency should provide a quantitative bank-migration rate estimate and demonstrate that the 15-foot setback is adequate for the full design life of the structure.

Say something only you can say. The law requires the agency to consider and respond to substantive comments, and specifics are what make a comment substantive.

Every point is checked against the agency’s own document ↗. 7 findings verified against the text, word for word.