Stop the unlawful FONSI for utility projects across 13 million Southern Region acres

U.S. Forest Service · National Forests in Alabama, AL

What
The agency is asking the public to accept a FONSI covering 1,500-plus active authorizations on 9,580 miles of national forest land while admitting it has not completed ESA or NHPA compliance.
Where
National Forests in Alabama, AL
By when
Comments to U.S. Forest Service by November 20, 2026.Date from Forest Service CARA comment page ↗, read October 29, 2026.

What to ask forAll 8 points →

The agency must correct the FONSI to accurately describe the selected action or withdraw and reissue both documents together so the public can comment on a consistent record.

Where these four lines come from
  • WhatOur plain-English read of the Forest Service project page ↗. Check it against the agency’s own words under Case.
  • WhereThe places and states the project page names, as PLAN read them.
  • over 1,500 active authorizations“over 1,500 active authorizations for linear utilities and communications uses on approximately 9,580 miles of NFS land covering 38,499 acres” Purpose and Need Open the document ↗
  • approximately 9,580 miles“over 1,500 active authorizations for linear utilities and communications uses on approximately 9,580 miles of NFS land covering 38,499 acres” Purpose and Need Open the document ↗
  • 38,499 acres“approximately 9,580 miles of NFS land covering 38,499 acres (note that some of these uses overlap so actual land use is lower)” Purpose and Need Open the document ↗
  • By whenNovember 20, 2026, from Forest Service CARA comment page, the notice text ↗: “requested through 11/20/2026 11:59:59 PM (Eastern Standard Time)”. Read October 29, 2026.
  • Read from PLAN’s record November 13, 2026.
Now make it count7 days left

Two ways to be heard on this, and both count. Comment for the legal record, then call the members who answer to you.

Comment now

What to say

Make these points, in your own words

  • The FONSI describes the selected action as a framework for 'emergency response actions and issuance of closure orders,' but the EA itself proposes a framework for routine utility and communications special uses including new construction, ROW expansion, and long-term vegetation management.Read the point +

    This internal contradiction means the FONSI does not actually evaluate the action the EA analyzes. The agency must correct the FONSI to accurately describe the selected action or withdraw and reissue both documents together so the public can comment on a consistent record.

  • Appendix A's trend data, which is the empirical foundation for the FONSI, shows that Threatened and Endangered species received only 2 mentions and Fish/Aquatic Resources only 1 mention across 503 reviewed projects, yet Appendix D lists hundreds of listed species across all 14 forests.Read the point +

    The near-total absence of ESA and aquatic species analysis in the underlying project record means the conclusion that effects are predictably minimal is not supported by the data the agency itself cites. The agency should commission and incorporate a species-specific analysis drawing on projects that actually documented listed-species interactions before issuing a FONSI.

  • The EA states the proposed action includes 'construction of new utility lines, expansion or realignment of existing ROWs, and associated long-term vegetation management' outside previously disturbed areas, yet the FONSI's bounded-scope rationale claims effects are constrained because activities are 'typically confined to existing disturbed areas' and the EA 'excludes new permanent infrastructure.'Read the point +

    These two statements directly contradict each other. The agency must reconcile this conflict and analyze the full range of new-disturbance activities in a supplemental analysis or EIS before authorizing any project under this framework.

  • The EA covers over 1,500 active authorizations on approximately 9,580 miles of NFS land covering 38,499 acres, plus 130 active applications and 57 expiring authorizations, yet the cumulative effects analysis contains no numerical estimate of total acreage disturbed annually, no projection of new ROW miles, and no aggregate assessment of combined impacts across forests.Read the point +

    NEPA requires analysis of cumulative effects of past, present, and reasonably foreseeable actions. The agency must prepare a quantitative cumulative effects analysis before issuing a FONSI for a region-wide framework of this scale.

  • The Appendix A trend report, which the agency uses as the primary empirical basis for the programmatic framework, found zero projects with beneficial or improvement effects and recorded 44 projects with adverse or negative effects, yet the body of the EA repeatedly concludes that effects are consistently minimal or non-significant.Read the point +

    The agency never explains why 44 adverse-effect projects do not trigger additional analysis or preclude a FONSI. The agency must explain in the decision record how 44 documented adverse or negative outcomes are consistent with a finding of no significant impact, or prepare an EIS.

Say something only you can say. The law requires the agency to consider and respond to substantive comments, and specifics are what make a comment substantive.

Every point is checked against the agency’s own document ↗. 8 findings verified against the text, word for word.